A can do a particular work in 6 days . B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?

A. Rs. 380
B. Rs. 600
C. Rs. 420
D. Rs. 400